Tuesday; 4/25/17 - Milling: We will start with Soundview Drive Horseshoe and East Gate; we will then move to Grant Street, Bleeker Street and North Bleeker Street; we will then move to Village Woods Road; we will then finish with Brewster Drive and Chambers Court. All milling will be done in 1 day. Friday; 4/28/17 [...]